Recreation Center Renovation Update

Construction progress for May includes:

Phase 1 renovation of the lower level multipurpose rooms: 

Phase 2 renovation of second floor fitness floor & personal training:

Estimated Project Schedule is as follows:

Completion of Phase 1 (Lower Level):                                                         June 26

Begin Phase 2 (Upper Level Stretching Area and Group Ex Room):     June 26

Begin Phase 3 (Facility Closure):                                                                  Aug 21–31

Estimated Grand Opening:                                                                           Sept. 1

For more information on the Recreation Center Renovation project, click here