Parks & Golf Operations Center Project Update

This past month there was tremendous progress buttoning up the shell of the building. The roof is installed,  roof top units are in place, window frames and most of the windows are installed. Concrete on the first floor was poured. Site work also  progressed with the curb work throughout the site, soil placement, seeding, installation of the fuel island, North Shore gas installation, and completion of the material storage bins.

Looking ahead, crews will apply the top finishing coat to the second floor, begin installation of interior masonry walls, and complete the parking lot.

For more information on this project, click here.

Questions? Comments?  Contact Amalia Schwartz, aschwartz@pdhp.org or 847.579.4090.