Sunset Valley Clubhouse Renovation Update

Demolition of the clubhouse site began the week of March 12 and is nearing completion. Work on the outside of the clubhouse  included the removal of landscaping vegetation, bushes and trees, asphalt, concrete pads and sidewalk surrounding the clubhouse as well as the starter hut, concrete slab, and light ballads.  Inside the clubhouse work included removal of existing drywall, plaster and gypsum on the walls and ceilings; doors, windows, framing and exterior wall for new storefront glazing were removed and boarded; flooring was removed;  locker rooms have been demolished; electrical and plumbing fixtures were removed; and a structural beam has been removed to allow for a consistent ceiling height.

Additional progress includes installation of the footings, foundation and piers for the outside patio that wraps around the north, east and south of the building and installation of down spout drains.   Inside construction will begin this week.

For more information on the project, click here