A  new centralized Parks and Golf Operations Center will be located at the current site of Golf Maintenance building (1240 Fredrickson) on the west side of the Sunset Valley Golf Course.  The new facility will replace both the Golf Maintenance Facility and the District’s Parks Maintenance Facility located south of the Sunset Valley clubhouse.  Both facilities are inefficient and inadequate for the current and future needs of the Park District and Sunset Valley.

Please review the proposed plan below and e-mail Liza McElroy, Executive Director (lmcelroy@pdhp.org) or Amalia Schwartz, Senior Planner (aschwartz@pdhp.org)  with your comments, questions, or feedback.
View the proposed plans: POGO Project Plan.


6/1/17 Update

With demolition complete, crews continue to work on site grading. Site grading will be ongoing for the next few weeks. Work on the building foundation system will begin mid-June.

 

5/25/17 Update

This week crews will complete demolition of the building and site clearing.  Next week, excavation and grading of the site will begin.  

 

5/12/17 Update

This week crews have been preparing the site for demolition including the installation of fencing and site clearing. Contractors will begin demolition on Monday, May 15. 

5/5/17 Update

Construction is set to begin the second week in May on the new park and golf operation facility which will provide a consolidated efficient space for golf and park operations staff.  The new building will be located south of the Hidden Creek Aqua Park, West of Sunset Valley Golf Course, in the current location of the existing golf maintenance facility.

In preparation for demolition, contractors will be on site the week of May 8th removing 54 trees to the north and east of the site make way for the new building.  109 trees will be replanted on site this Fall. Demolition of the golf maintenance facility is scheduled to begin the week of May 15th

 

4/13/17 Update

The Plan and Design Commission recommended the Park and Golf Operations Center project for City Council approval. The project will be discussed at the Monday, April 24 City Council Meeting. The meeting is scheduled for 7:30 pm at City Hall, 1707 St Johns Ave. 

Site work will begin this May with demolition of the existing building and site grading . Construction of the building will begin in June.

 

2/2/17 Update 

The project plans have been updated based on feedback from the community and the Plan and Design Commission. The updated plans will be presented at the Plan and Design Commission meeting scheduled for 7:30pm on Tuesday, February 7 at City Hall.

View the proposed plans: POGO Project Plan

Target Schedule: Please check back for continued updates to the schedule. 
The project is currently under City Review
Site work: Start Spring 2017
Construction: Start Summer 2017

12/7/16 Update

A neighborhood meeting to review the proposed plans will take place on Monday, December 12 at 7 pm at the current Parks Operation Building located at 1390 Sunset Rd.

The project team will present the proposed project application to the City Plan & Design Commission at their public meeting at 7pm on Tuesday, January 3 at City Hall.

4/4/16 Update

Initial planning & design is in development for the new facility.

In late spring a Public Hearing will be held to formally introduce the project to the community and to collect resident feedback. Please continue to check back for more updates as the project progresses.

Below are photos of the current Parks and Golf Maintenance facilities located on opposite sides of Sunset Valley Golf Course.

 

Parks Maintenance Garage

Parks Maintenance Garage

Parks Maintenance Garage

Parks Maintenance Garage

Golf Maintenance Garage

Golf Maintenance Garage

Golf Maintenance Garage

Golf Maintenance Garage