Park Avenue Sand Ramp & Winch Electric Line Replacement
Start Date
Late Winter 2025
End Date
May 2025
Location
Park Avenue Boating Facility (8 Park Avenue)

The Park District was awarded $60,000 through the Illinois Department of Natural Resources’ Boat Access Area Development (BAAD) grant program to provide consistent access for boats utilizing the sand ramp. The project includes installation of a new “Yard Ramp,” to mitigate the sand ramp’s washout challenges, as well as the repair of the winch’s electric line.

Project Updates

Stay Up to Date on the Latest Renovations

May 22, 2025

The new sand ramp is now open!

May 22, 2025
April 18, 2025


The mounting structure for the new ramp has been installed and the sand ramp has been set in place.


Once final modifications are made, the ramp will be completed.

April 18, 2025
April 10, 2025

Work on the winch electric line has been completed.

April 10, 2025
March 20, 2025

Replacement of the winch electric line is currently underway.

The new sand ramp has been delivered to the site and will be set in place once the mounting structure is fabricated and installed.

The project is on track to be completed by late April.

March 20, 2025