Fontana-Pasquesi Park Basketball Court Renovation
Location
1790 Eastwood Avenue
Target Start Date
September 2025
Target End Date
October 2025

Fontana-Pasquesi’s Basketball Court is scheduled for replacement in fall 2025.

The renovation will remove the existing basketball court and replace it with a half court, and small youth half court. The shape will become a standard rectangle, replacing the existing curvy court.

The renovation will also involve work under the court, to address the cracking problem seen on the existing court. 

Concept Plan

Project Updates

Stay Up to Date on the Latest Renovations

November 5, 2025

The coloring and striping of the basketball court has been postponed until the Spring.

The construction fence will be taken down once the installation of the backboards and hoops is completed.
The basketball court will be open until the coloring/striping occurs.

November 5, 2025
October 31, 2025

Crews will be on site this weekend to install the basketball posts, the backboards and hoops will be installed once the posts are set.

Coloring/striping of the court is expected to begin in the next couple of weeks.

October 31, 2025
October 10, 2025

Site restoration work is nearly complete.

Up Next: The court will be colored/striped and the basketball hoops installed.

October 10, 2025
October 1, 2025

The court paving has been completed.



Next the crews will work on site restoration and coloring/striping of the court.

October 1, 2025
September 18, 2025

Installation of the drainage tile and stone base has been completed.

The court is expected to be paved on Wednesday, September 24.

September 18, 2025
September 17, 2025

Construction has started!

Crews were on site yesterday to start demolition of the basketball court.



Once demolition was completed, work began to install the drainage tiles and stone base layer of the court.

September 17, 2025
August 29, 2025

Construction is expected to begin the week of September 15.

When the construction fence goes up, the basketball court will remain closed until construction is complete.

Check back here for updates as the project moves along.

August 29, 2025