Tue, Sept 3 – Centennial Ice Arena Update: Over the next two weeks, contractors will work in the Centennial Ice Arena parking lot to correct a construction error on the west side ADA parking spaces. The building, turn-around, the remainder of the parking lot including the two ADA parking spaces on the south side of the lot remain open during construction.

Danny Cunniff Maintenance Building Improvements Project
Location:
2700 Trail Way
Project Start:
October 2023
Project End:
December 2023

Danny Cunniff Park’s Maintenance Building will be undergoing several improvements this fall.

Project Components:

  • both restrooms will be renovated, including ADA upgrades
  • roof replacement
  • gutter installation

Project Updates

Stay Up To Date on the Latest Renovations

November 30, 2023

Renovation work on the restrooms is nearing completion. Work is expected to be completed the week of December 18.

November 30, 2023
October 18, 2023

Demolition work is complete and renovations are underway for the restrooms. The roof replacement has been completed and the gutters will be installed soon.

October 18, 2023
October 9, 2023

Demolition work began today on the maintenance building restrooms.

October 9, 2023