To accommodate crews working on the Senior Center, from Thurs., Aug 1 through Sat., Aug 3 the Recreation Center elevator will be out of service. On Thurs., Aug 1, from 8am to noon, the Recreation Center locker rooms will be closed and the entrance to the Center will be limited to the southeast side, next to the lobby and the emergency exit.  Also, on Thurs., Aug 1, from noon to 5pm, the Recreation Center’s pool and locker rooms will be closed and the hot water will be shut off. We appreciate your patience during this time.

Heller Nature Center Blue Trail Improvements Project
Location
2821 Ridge Road
Start Date
July 11, 2023
End Date
August 2023

The Park District of Highland Park is working to improve Heller’s Blue Trail. During the renovation of the Blue Trail, the trail will be closed and will not reopen until work has concluded.

This project requires regrading of the trail and replacement of the trail material. The route will not change as part of this renovation.

Updates

August 2, 2023

The Blue Trail Renovations have been completed, the trail is now open for use.

August 2, 2023
July 11, 2023

The contractor has mobilized, the equipment has arrived on site and excavation work will begin this week.

July 11, 2023