Park Avenue South Boat Storage Lot Restoration
Location
Park Avenue Boating Facility (8 Park Avenue)
Start Date
Late Winter 2025
End Date
April 2025

Due to unforeseen conditions, restoration of the South Boat Storage Lot at Park Avenue Boating Facility will not be able to be completed prior to Memorial Day. Therefore, construction is being deferred to late winter/early spring 2025.

Restoration work includes removal and replacement of damaged parking lot sections and walls. During construction, access to the boat storage lot will be closed.

Project Updates

Stay Up to Date on the Latest Renovations

April 14, 2025

The majority of the sheetpile that will form the parking lot has been driven into the ground.





Once completed, crews will cut the sheets, install drainage, and backfill the lot.

The project is on track to be completed late April.

April 14, 2025
March 20, 2025

Demolition is nearing completion and the crews will begin to prepare the site for installation of the sheet pile, which will serve as the border for the reconstructed lot.

A crane was delivered today. Additional equipment and sheet pile will be delivered in the coming days.



Driving of the sheet pile is expected to begin late next week.

The project is on track to be completed by April.

March 20, 2025
March 12, 2024

Construction is scheduled to begin on March 19, 2024

March 12, 2024