To accommodate crews working on the Senior Center, from Thurs., Aug 1 through Sat., Aug 3 the Recreation Center elevator will be out of service. On Thurs., Aug 1, from 8am to noon, the Recreation Center locker rooms will be closed and the entrance to the Center will be limited to the southeast side, next to the lobby and the emergency exit.  Also, on Thurs., Aug 1, from noon to 5pm, the Recreation Center’s pool and locker rooms will be closed and the hot water will be shut off. We appreciate your patience during this time.

Rosewood Park Playground Renovation
Location
45 Roger Williams Ave
Target Start Date
April 2025
Target End Date
July 2025

Rosewood Park’s playground is scheduled for replacement next year. In preparation, the Park District of Highland Park is beginning the planning process for Rosewood’s 2025 update this summer.

The playground design process is collaborative, and the community will have various opportunities to get involved.

Join the conversation!

Upcoming Community Engagement Opportunities

The Planning and Projects team will be at Rosewood Park to share playground equipment options and collect feedback (*weather permitting, check this page for any schedule changes). Join us anytime during the following dates and times to learn about the project and share your feedback.

  • Wednesday, July 24 from 9-11am – Stop by to share your feedback and participate in a kid’s craft activity (while supplies last)
  • Monday, July 29 from 3-5pm – Stop by to share your feedback and enjoy popsicles (while supplies last)
  • Tuesday, July 30 from 5-7pm – Stop by to share your feedback and enjoy popsicles (while supplies last)

If you cannot make it to the park during one of these times, please take the survey!

Get Updates!

If you are interested in receiving notifications about this project, please fill out the form below.

Process
Target Start
Target End
Design
July 2024
October 2024
Bid/Award
November 2024
January 2025
Construction
April 2025
July 2025