Sunset Woods Playground Improvements Update

May 12, 2022

Finally, an entirely dry week! Great progress has been made at the construction site. Most notably, stage 2 of the rocket ship is installed, and crews are starting to pour the concrete for the walkways. About 70% of the playground equipment is installed, and crews will be working on the remaining pieces next week, including the net climber. Crews are also working on improvements to the park entrance, including new benches, a bike rack, a water fountain, and landscaping. The project is on track to be completed by the week of June 20.